CARA MENGHITUNG ADUKAN MORTAR [ metode B.O.W ]

CARA MENGHITUNG ADUKAN MORTAR [ metode B.O.W ]

Koef bahan berdasar B.O.W :
Semen = 0.76
Pasir = 0.675

Artinya dalam 1 m3 pasir terdiri dari 0.675 m3 pasir + 0.325 rongga udara
Bj Semen = 1250 Kg
1 zak = 50 kg


Analisa B.O.W –  G 13
*****************************************
=====>   1 m3 adukan mortar 1 : 1 
*****************************************

1 m3 semen  ------> jadi adukan =  1 * 0.76 = 0.76  m3
1 m3 pasir -------> jadi adukan =  1 * 0.675 = 0.675 m3
=========================================================
2 m3 material -----> menghasilkan  adukan mortar  = 1.435  m3


1 m3 adukan Mortar = 1 : 1  ===> dibutuhkan bahan…
--------------------------------------------------------------------------
Semen = 1/1.435 * 1 m3 = 0.7 m3 = 875 kg = 17.5 zak
Pasir = 1/1.435 * 1 m3 = 0.7 m3


Analisa B.O.W –  G 14
*****************************************
=====>   1 m3 adukan mortar 1 : 2 
*****************************************

1 m3 semen -----> jadi adukan =  1 * 0.76 = .76  m3
2 m3 pasir -----> jadi adukan =  2 * 0.675 = 1.35 m3
=========================================================
3 m3 material ----> menghasilkan  adukan mortar  = 2.11  m3


1 m3 adukan Mortar = 1 : 2  ===> dibutuhkan bahan…
--------------------------------------------------------------------------
Semen = 1/ 2.11 * 1 m3 = 0.47 m3 = 587.5 kg = 11.75 zak
Pasir = = 1/ 2.11 * 2 m3 = 0.95 m3



Analisa B.O.W – G 16
*****************************************
=====>   1 m3 adukan mortar 1 : 3 
*****************************************

1 m3 semen  ------> jadi adukan =  1 * 0.76 = .76  m3
3 m3 pasir -------> jadi adukan =  3 * 0.675 = 2.076 m3
=========================================================
4 m3 material -----> menghasilkan  adukan mortar  =  2.785  m3


1 m3 adukan Mortar = 1 : 3  ===> dibutuhkan bahan…
--------------------------------------------------------------------------
Semen = 1/ 2.785 * 1 m3 = 0.36 m3 = 450 kg = 9 zak
Pasir = 1/ 2.785 * 3 m3 = 1.08 m3





Analisa B.O.W –  G 19
*****************************************
=====>   1 m3 adukan mortar 1 : 4 
*****************************************

1 m3 semen  -------> jadi adukan =  1 * 0.76 = .76  m3
4 m3 pasir --------> jadi adukan =  4 * 0.675 = 2.70 m3
=========================================================
5 m3 material ------> menghasilkan  adukan beton  =    3.46  m3

1 m3 adukan Mortar = 1 : 4  ===> dibutuhkan bahan…
--------------------------------------------------------------------------
Semen = 1/3.46 * 1 m3 = 0.29 m3 = 362.5 kg = 7.25 zak
Pasir = 1/3.46 * 4 m3 = 1.16 m3







******************************************************
=====>  1 m3 adukan plesteran / mortar  1 : 5 
******************************************************

1 m3 semen  ------> jadi adukan =  1 * 0.76 = .76  m3
5 m3 pasir -------> jadi adukan =  5 * 0.675 = 3.375 m3
===============================================================
6 m3 material -----> menghasilkan adukan mortar  =  0.76 + 3.375 = 4.135  m3


1 m3 adukan mortar = 1 : 5  ===> dibutuhkan bahan…
-----------------------------------------------------------------------
Semen = 1/4.135 * 1 m3 = 0.2418 m3 = 302.2975 kg = 6.0459 zak
Pasir = 1/4.135 * 5 m3 = 1.2092 m3



CATATAN :
Analisa B.O.W –  G 46
1 m2 plesteran setebal 15 mm diperlukan 0.018 m3 mortar perekat.
1 m2 plesteran setebal 10 mm diperlukan 0.012 m3 mortar perek